ERP-Integrations IICS Team Sprint Review 53

This sprint focused on a few key stories and tasks including:

  • Madison Alma – Hermes replacement
    • Continue Testing New Alma Input Selection Criteria
    • Hermes/Alma – Additional exception Processing
    • Met with stakeholders to adjust settings to how shipping noted in Alma to allow for Workday Integration
  • Stout Touchnet Development Collaboration – Initial POC mapping for Submit Cash Sale EIB INT429 utilizing UW Stout generic Workday Customer, Sales items and FDM crosswalk
    • Continued with work to include actual Workday Sales Items in place of generic placeholders after meeting on 9.4