This was an extended 4-week sprint due to Workday Go-Live, and focused on several key stories and tasks including:
- Migrate UWMIL T2 Parking Person to Production and Set Recurrence Schedule (AI-545)
- Migrate BP Logix to Production and Set Recurrence Schedule (AI-431)
- Migrate 4Ward Full File to Production and Set Recurrence Schedule (AI-549)
- Testing – FM Systems Person Extract for FP&M (AI-541)
- Testing – FM Systems Grant/Fund Extract for FP&M (AI-448)
- Validate Initial Production 4Ward File (AI-530)
- Validate Initial Production BP Logix Provisioning File (AI-531)
- Develop – FM Systems for FP&M – Location EIB (AI-495)
- Migrate ZRex to Production and Set Recurrence Schedule (AI-543)
- Testing – Terra Dotta Person Integration (AI-449)
- Migrate Terra Dotta to Production and Set Recurrence Schedule (AI-550)
- ASP IICS EAP Production Processing Readiness (AI-529)
- Perform Full System/Smoke test of all IICS EAP Pipeline Processing (AI-536)
- Retrofit Redshift Account Changes to IICS EAP Pipelines (AI-500)
- Deliver Critical 6/24 EAP Release Datasets (AI-540)
- Determine Solution for Handling Timestamp with Milliseconds (AI-579)
- POC – Incorporate Alternate Views to Protect from EAP Column Width Changes (AI-575)
- IICS EAP Implement Logging mechanism for School of Education(WIDA) Workflows (AI-533)
- Deliver Additional EAP Tables to Grad School, July 2025 (AI-569)
- Delivery Additional EAP Tables to Grad School OVCR, July 2025 (AI-570)
- Hermes/Alma Invoice Data – Deploy to Production (AI-283)
- Migrate UWMIL T2 Parking FDM to Production and Set Recurrence Schedule (AI-544)
- Migrate Database Code to Production and Set Recurrence Schedule (AI-432)
- Alma/Hermes IICS Ad-hoc Run for 7/10/2025 (AI-566)
- POC – Email Notification of Database Data Load Stats to SCD’s (AI-583)